  Jinan Jinkui Tower Machine shares the relevant settings of the tower crane at the construction site. The setting of the tower crane has certain technical requirements. Today we will talk about the s
  Jinan Jinkui Tower Machine shares the relevant settings of the tower crane at the construction site. The setting of the tower crane has certain technical requirements. Today we will talk about the setting of the tower crane on the construction site.
  (1) The distance between the tower crane center of the orbital tower crane and the external wall of the building should take into account the protruding parts of the building, scaffolding, safety net,safety space and other factors, generally not less than 3.5 meters. When multiple tower cranes are arranged at the same site at the same time, necessary anti-collision measures should be taken to maintain the minimum distance between the two tower cranes to ensure the safety of the tower crane cross work.
  (2) The proposed building is adjacent to the street. The tower arm of the tower crane can cover the sidewalk, and the tower rail of the tower crane should be arranged on the inner side of the building as much as possible.
  (3) When the tower crane and the adjacent high-voltage line do not reach a safe distance, the protective frame shall be erected, and the angle of rotation shall be limited to prevent accidents caused by the tower crane operation.
  Mobile tower cranes, vertical, the lowest position of the tower crane in the high position (such as tower crane hooks, including hanging objects) and the vertical height of the lowest position of the lower tower crane shall not be less than 5 meters.
 